COVID-19 continues to make significant impacts on our economic climate, leaving many businesses seeking clarity on their rights, obligations, and relief that might be available. With the current situation, a force majeure clause may provide relief under construction and commercial contracts.
Simply stated, “Force Majeure” provisions can excuse a party’s inability to meet contractual obligations due to circumstances that are outside the reasonable control of the non-performing party. Common circumstances include:
(a) an act of God, landslide, tornado, earthquake or similar occurrence, fire, explosion or other casualty or flood;
(b) an act of the public enemy, terrorist act, war, blockade, insurrection, riot, general arrest or restraint of government and people, civil disturbance or similar occurrence or sabotage; and
(c) labor strikes, lockouts, work stoppages, boycotts, and walkouts.
The burden of demonstrating a contractual force majeure event typically rests with the party seeking to avoid its contractual obligations. Importantly, the scope and application of force majeure provisions varies by state, so each provision must be carefully evaluated. Some states will narrowly interpret force majeure provisions and only permit the application if it is specifically listed. Other states enforce broader interpretations and enforce general catch-all categories.
An important factor to consider when invoking a force majeure clause is that the party wishing to invoke must prove that the force majeure event caused the party to be unable to fulfil its obligations under the contract. A force majeure clause also generally requires the party invoking the clause to use reasonable endeavors to avoid the effects of force majeure to the extent possible, and that there are no reasonable alternative means for performing under the contract. Many provisions only grant equitable schedule adjustments and do not provide relief for cost adjustments.
Each force majeure clause is different and must be carefully reviewed by counsel. However, a force majeure clause may provide relief for COVID-19 if the clause includes events such as:
- diseases, pandemics, epidemics, or other national health emergency
- the unavailability of labor and/or materials as a result of any health emergency
- any governmental restrictions in respect of labor or materials in connection with any health emergency
- any declaration of a state of emergency
- compliance with a law or governmental order, rule, regulation or direction;
- any action taken by government or public authority, including imposing embargo, export restriction, or other restriction or prohibition;
- delays by suppliers or materials shortages;
- difficulty or increased costs in obtaining workers, goods, or transport; or
- other circumstances affecting the supply of good or services.
- Review the applicable force majeure provisions to determine what situation is covered.
- Confirm the notice requirements under the contract. This is critical, as most force majeure provisions have time limitations on reporting the force majeure event after it occurs and contain waiver provisions if notice is not timely provided.
- When providing notice of a claim, provide as much information about the impact of COVID-19 on the project. Include all schedule and cost impacts, and when the force majeure event is expected to conclude. If complete information is not available, your notice should state that additional information becomes available.
- Be careful that any notice does not trigger a default, anticipatory breach or right to suspend or terminate by the other party. Carefully review the remedy provisions for force majeure events.
- Document all schedule and cost impacts, including creating separate job-cost codes for COVID-19 impacts.
- Request that all downstream suppliers and vendors provide assurances that they will not be impacted by COVID-19, and consider whether and when an alternate subcontractor, vendor or supplier should be retained.
- Develop contingency plans for labor and material shortages.
- If you have received a force majeure notice from one of your subcontractors, vendors or suppliers, consider whether that notice triggers a force majeure event for upstream report purposes.
Readers of this article should contact an attorney to obtain advice with respect to any particular legal matter. No reader, user, or browser of this site should act or refrain from acting on the basis of information on this site without first seeking legal advice from counsel in the relevant jurisdiction. Only your individual attorney can provide assurances that the information contained herein – and your interpretation of it – is applicable or appropriate to your particular situation. Use of, and access to, this website or any of the links or resources contained within the site do not create an attorney-client relationship between the reader, user, or browser and website authors, contributors, contributing law firms, or committee members and their respective employers.